Job Index
|
Below are descriptions and pictures of some of the projects which
Orders Construction has completed over the years. You may browse the list, or
use the index to find a specific job. Then click on its picture to see more.
|
PROJECT: Beaver Creek Bridge
LOCATION: Wheeling, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Construction of twin 765 foot, six span bridges
of up to 200 feet in height.
PROJECT COST: $6,200,000.00
|
|
PROJECT: Martinsburg Wastewater Treatment Plant
LOCATION: Martinsburg, WV
OWNER: City of Martinsburg
DESCRIPTION: Major upgrade of a city's wastewater facility.
PROJECT COST: $5,200,000.00
|
|
PROJECT: Fort Henry Bridge
LOCATION: Wheeling, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Complete renovation of bridge and approaches
on I-70 over the Ohio River.
PROJECT COST: $12,400,000.00
|
|
PROJECT: Wiley Ford Bridge
LOCATION: Cumberland, MD
OWNER: Maryland State Highway Administration, Annapolis, MD
DESCRIPTION: New bridge and approaches on US Route 220
over the Potomac River including a four span temporary detour bridge of 473 feet.
PROJECT COST: $3,700,000.00
|
|
PROJECT: Winfield Interchange
LOCATION: Winfield, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Complete reconstruction of an interstate
interchange including bridges, excavation, paving, drainage, signs, signals,
and lighting.
PROJECT COST: $4,200,000.00
|
|
PROJECT: South Branch Railroad Upgrade
LOCATION: Moorefield, WV
OWNER: West Virginia Railroad Authority, Moorefield, WV
DESCRIPTION: Repair and upgrade of flood damaged railroad bridges.
PROJECT COST: $950,000.00
|
|
PROJECT: Beckley Water Treatment Plant
LOCATION: Beckley, WV
OWNER: Beckley Water Company, Beckley, WV
DESCRIPTION: Complete construction of a new water
treatment plant.
PROJECT COST: $3,800,000.00
|
|
PROJECT: Ronceverte Bridges
LOCATION: Ronceverte, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Demolition and replacement of two structures over
the CSX railroad and Greenbrier River.
PROJECT COST: $4,600,000.00
|
|
PROJECT: Meadow River Bridge
LOCATION: Fayette County, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Construction of a new 1200 foot, six span deck
truss and beam bridge up to 210 feet high.
PROJECT COST: $8,900,000.00
|
|
PROJECT: 24th Street Pump Station Upgrade
LOCATION: Huntington, WV
OWNER: West Virginia American Water, Charleston, WV
DESCRIPTION: Upgrade of water intake with Zebra Muscle control.
PROJECT COST: $490,000.00
|
|
PROJECT: Howards Creek Watershed
LOCATION: White Sulphur Springs, WV
OWNER: Natural Resources Conservation Service, Washington, DC
DESCRIPTION: Stream improvements including rip-rap, pile
walls, concrete walls, and wier construction.
PROJECT COST: $3,400,000.00
|
|
PROJECT: Process System Upgrade
LOCATION: South Charleston, WV
OWNER: Clearon Corporation, South Charleston, WV
DESCRIPTION: Front end process improvement for
cyanuric acid production.
PROJECT COST: $1,530,000.00
|
|
PROJECT: Poplar Camp Bridge
LOCATION: Wythe County, VA
OWNER: Virginia Department of Transportation, Richmond, VA
DESCRIPTION: Demolition and replacement of a bridge on
US Route 52 over the New River.
PROJECT COST: $1,800,000.00
|
|
PROJECT: Martinsburg -- Baker Heights
LOCATION: Martinsburg, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Complete upgrade including grading, drainage,
utilities, and pavement of a section of WV Route 9.
PROJECT COST: $5,300,000.00
|
|
PROJECT: Barrackville Covered Bridge
LOCATION: Fairmont, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Complete historical reconstruction of a covered bridge.
PROJECT COST: $1,100,000.00
|
|
PROJECT: Fayette Station Bridge
LOCATION: Fayette County, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Complete historical reconstruction of a three
span truss bridge over the New River.
PROJECT COST: $4,200,000.00
|
|
PROJECT: Elkem Metals Bridge
LOCATION: Alloy, WV
OWNER: Elkem, Oslo, Norway
DESCRIPTION: Design and construction of a new bridge for
an entrance to an industrial facility, including mechanically
stabilized earth approaches.
PROJECT COST: $1,500,000.00
|
|
PROJECT: Route 102 Upgrade
LOCATION: Tazwell County, VA
OWNER: Virginia Department of Transportation, Richmond, VA
DESCRIPTION: Major highway relocation including a 712 foot long,
four span, steel girder bridge and 800,000 cubic yards of excavation.
PROJECT COST: $7,200,000.00
|
|
PROJECT: East River Bridge
LOCATION: Mercer County, WV
OWNER: West Virginia Department of Transportation, Charleston, WV
DESCRIPTION: Replacement of deck and steel of twin 490
foot bridges on I-77 in a single season.
PROJECT COST: $4,000,000.00
|
|
PROJECT: Fayette Raw Water Pumping Station
LOCATION: Fayette County, WV
OWNER: West Virginia American Water, Charleston, WV
DESCRIPTION: New construction of major pumping station, lines, roads, and retaining walls.
PROJECT COST: $6,700,000.00
|
|
PROJECT: 40th Street to Institute
LOCATION: Kanawha County, WV
OWNER: Subcontract to West Virginia Paving, Dunbar, WV
DESCRIPTION: Slip-form of complex median wall on I-64 widening.
PROJECT COST: $2,000,000.00+
|
|
[Home]
[History]
[Services]
[Safety]
[Past Projects]
[Email]
[Awards]
[Location]
[References]
[Memberships]
[Employment]
|
|
Copyright © 1999-2004.
Orders Construction Company, Inc.
All rights reserved.
Contact webmaster regarding this site.
|
|
|
|